Bicriteria scheduling problem on parallel machine
Keywords:
Scheduling, dependent setup times, bicriteria.Abstract
This paper shows the parallel machine
scheduling problem with sequence dependent
set up times. The purpose is to schedule the
jobs to minimize the weighted sum of
average completion time and average
tardiness of the jobs. The aim is to maintain a
good service with minimum work in process.
This research analyzes the behaviour of six
simple heuristics easily to implement for
practitioners which are the combination of
three simple procedures to obtain an initial
solution and two improvement procedures;
one that acts on a neighbourhood formed
from the sequences for each machine and
another that acts on the neighbourhood
established from the sequences in each
machine. The results show that the second
improvement procedure, which is closer to the
matter of the problem, leads to better results.
According to this result, the performance of
the initial procedures, when the weighted of
the two criteria are varied, has been studied.
The results of the test show that, for more
balanced criteria, the initial procedures which
consider those criteria lead to better results.